案 Notice
Seoul power feed transfer — completed
SEL-1
Feed B at SEL-1 was moved to new switchgear between 16:00 and 19:00 UTC on 18 June. Racks ran on feed A alone for two hours and eleven minutes, inside the design margin, and no generator start was required. No instance saw an interruption. The matching transfer on feed A is not yet scheduled; it will be posted here first.
Posted 2026.06.18 · the whole board · the availability commitment
← 2026.06.302026.06.05 →
三 Nothing is edited away
Every incident is published here whatever its size, planned work is announced at least seven days ahead, and a notice is corrected by a new notice that references it rather than by editing this one. The archive runs from 2026.02.02. Read all of it.